TESS FENWICK

Level 3 Deck Beam Poured by TESS FENWICK

The Level 3 deck beam has now been poured.  This week is going to be busy with the cedar cladding starting to be fixed, the stairs starting to be formed and the pour for the deck itself on Friday.  Keep an eye out for the concrete pump!

Northern Deck Poured by TESS FENWICK

It has been a busy few weeks on site.  The northern deck has been poured and the Level 3 roof has been covered in.  The ceiling is being framed up and the cedar cladding has now arrived onsite.  We are now down to the last few concrete pours!

Northern Deck Almost Complete! by TESS FENWICK

The windows are tacked in on part of Level 2 and the northern deck perimeter beams have now been poured.  The next step is pouring the northern deck itself ... the wait is now on for the cedar cladding to arrive.