The Finishing Touches by TESS FENWICK

The screens have arrived and are currently being installed.  The custom NYC street map reflects the clients love of Manhattan.  In summer the map will be cast onto the floor in the morning sun.

Finishing Details by TESS FENWICK

The master bathroom tiling has now been completed and the tilers' are moving quickly throughout the house.  The wardrobe units have been installed and the electrician is wiring to them now.  The Level 3 deck tiles are in place.  They sit on a deck jack system which allows any water to drain through the negative and move away underneath the tiles.  Any furniture on the tiles can then sit level.

The Finishing Phase by TESS FENWICK

The central stair wall has been plastered, the underfloor heating cables are being laid and the lighting is starting to be installed. Next weeks the scaffolding on the eastern façade will come down. 

Settling into the Neighbourhood by TESS FENWICK

Gib board is currently being fixed and stopped while Kepka's have started on the cedar ceiling in the axis.  The vertical cedar garage door has been installed and the Symonite fascias are nearing completion.  Landscaping (by South Pacific Landscapes) has begun ... watch how the house settles into the surrounding neighbourhood.